Elgin Shop – Finishing the Foundation

They preped the foundation today, I tried to put as much of the electrical conduit in the foundations as I can. There are 4 zones per side. One in the floor and 3 about10 feet apart. I will show more pictures when I get to the wiring.
You can also see the 4 floor plug boxes. The main conduit is 1 inch and the side branches are 3/4 inch.
Here they are Pouring the cement:

Slab all finished up.

It took 3 days, a stuck cement truck, a dumped cement load,and a lot of Honey Buns. But is is finished.

Found the water main to the house!

Well we needed 3 more loads of dirt for the shop, after 9 loads already delivered to the same spot we discovered that the water line was not where we thought it was:
After a little digging and cleaning it was ready to fix. Really sucks when it is cold BTW:

Quick and dirty Repair! It is cold and the family needs water, like many things you dont realize how much until it is gone!
No to continue with the shop!